Construction and operation of the 10.4 MW Khrami 7 HPP on the Khrami River of "Sakenergo" LLC and the project of laying a 35 kV power transmission line

Kvemo Kartli, Tetri Tskaro, Village Kosalari, Tetritskaro Municipality, village Kosalar

The LEPL of the National Environmental Agency, under the Ministry of Environmental Protection and Agriculture of Georgia, is publishing the environmental impact assessment report of the planned activity.

The comments and opinions regarding the EIA report require submission in writing to the LEPL of the National Environmental Agency at the address: Marshal Gelovani Avenue, N34 Tbilisi, or via email at eia@mepa.gov.ge

The statement on the environmental decision-making:

Construction and operation of the 10.4 MW Khram 7 HPP on the Khrami River of "Sakenergo" LLC and the project of laying a 35 kV power transmission line

The comments and opinions require submission in writing  August 18, 2023, inclusive.

See the report and information in detail at the following link:- https://nea.gov.ge/Ge/GZSH/6050

The public discussion on the environmental impact assessment report of the planned activity will be held:

1. On August 4, 2023, at 12:00. Address: Tetritskaro municipality, village Kosalar public school building.

2. On August 4, 2023, at 16:00. Address: Municipality of Bolnisi, village Diswell Public School Building.