The scoping report of the project for construction and operation of the sewage system and treatment plant in Bakuriani township and Didi Mitarbi village of Borjomi Municipality by "United Water Supply Company of Georgia" LLC

Samtskhe-Javakheti, Borjomi, Borough Bakuriani , Samtskhe-Javakheti, Borjomi, Bakuriani Township, Borjomi Municipality, Bakuriani Township

The EIEC of the Ministry of Environmental Protection and Agriculture of Georgia is publishing the scoping report of the planned activity.

The scoping report of the project for construction and operation of the sewage system and treatment plant in Bakuriani township and Didi Mitarbi village of Borjomi Municipality by "United Water Supply Company of Georgia" LLC

The comments and opinions related to the scoping report for the planned activity require submission in writing to the National Environmental Agency by September 25, 2023, inclusive, at the address: Tbilisi, D. Agmashenebeli Avenue N150, or by e-mail: eia@mepa.gov.ge. 

For detailed information, see the environmental assessment portal at ei.gov.ge.

The public discussion of the scoping report on the planned activity will be held:

•  September 22, 2023, 14:00 Bakuriani cinema building, Borjomi municipality

The public discussion is open; any public representative has the right to take part in it as well as to submit comments and opinions.