The project of the construction and operation of the 110 kV overhead power transmission line connecting the 110 kV substation of Lukhun 2 HPP with the 110 kV substation "Oni 110" in the territories of Ambrolauri and Oni municipalities of "International Energy Corporation" LLC

Racha-Lechkhumi and Kvemo Svaneti, Ambrolauri, Village Uravi, Racha-Lechkhumi and Kvemo Svaneti, Ambrolauri municipality, Uravi village

The EIEC of the Ministry of Environmental Protection and Agriculture of Georgia is publishing the scoping report of the planned activities:

The project of construction and operation of the 110 kV overhead power transmission line connecting the 110 kV substation of Lukhun 2 HPP with the 110 kV substation "Oni 110" in the territories of Ambrolauri and Oni municipalities of "International Energy Corporation" LLC

The comments and opinions related to the scoping report of the planned activity require submission in writing to the National Environmental Agency by September 27, 2023, inclusive, at the address: Tbilisi, D. Agmashenebeli Avenue N150, or send them to e-mail: eia@mepa.gov.ge. 

For detailed information, see the link: http://ei.gov.ge/ka/info/8ce2019a-6cb9-41f1-a623-bf6755f048a8 

The public discussion of the scoping report on the planned activities will be held: 

• September 21, 2023, 16:00 village of Ambrolauri municipality Building of the Uravi Culture House
• September 22, 2023, 11:00 Oni Municipality House of Culture building (address: Kakhaberi St. N4)

The public discussion is open, any representative of the community has the right to take part in it as well as to submit comments and opinions.